Article R4534-30 of the French Labour Code

When the various components of a shoring system are assembled outside the excavation, the height of these components is at least equal to the total depth of the excavation.
To avoid any tipping over or displacement, the shoring, after being lowered into the excavation, is suitably wedged.

Original in French 🇫🇷
Article R4534-30


Lorsque les divers éléments d’un blindage sont assemblés hors de la fouille, la hauteur de ces éléments est au moins égale à la profondeur totale de la fouille.
Pour éviter tout renversement ou déplacement, le blindage, après avoir été descendu dans la fouille, est convenablement calé.

Need help with this article? Get help from a French lawyer

Our French business lawyers are here to help.
We offer a FREE evaluation of your case.
Call us at +33 (0) 1 84 88 31 00 or send us an email.

Useful links

You have a question in French Business Law?

Our French business lawyers are here to help.
We offer a FREE evaluation of your case.
Call +33 (0) 1 84 88 31 00 or send us an email.

All information exchanged through this website will be communicated to lawyers registered with a French Bar and will remain confidential.