Article R2194-2 of the French Public procurement code
The contract may be amended when, subject to the limit set out in article R. 2194-3, additional works, supplies or services, whatever their amount, have become necessary and were not included in the initial contract, provided that a change of contractor is impossible for economic or technical reasons relating in particular to requirements for interchangeability or interoperability with existing equipment, services or installations purchased under the initial contract.