Article R2192-27 of the French Public procurement code
Where the request for payment does not include all the documents and information required by law or by the contract, or where these are incorrect or inconsistent, the time limit for payment may be interrupted once by the contracting authority.For contracting authorities with a public accountant, this interruption may only take place before the expenditure is authorised.