The purchaser shall require the tenderer to justify the price or costs proposed in his tender if it appears to be abnormally low in relation to the works, supplies or services, including for the part of the contract that he intends to subcontract.
Justifications relating in particular to the following aspects may be taken into consideration:
1° The method of manufacture of the products, the arrangements for the provision of the services, the construction process;
2° The technical solutions adopted or the exceptionally favourable conditions available to the tenderer for supplying the products or services or for carrying out the work;
3° The originality of the tender;
4° The environmental, social and labour regulations in force at the place where the work is to be carried out;
5° Whether the tenderer has received any State aid.