Where the term of the contract is less than or equal to twelve months, the amount of the advance payment is set at between 5% and 30% of the initial amount of the contract inclusive of all taxes.
Where the term of the contract is greater than twelve months, the amount of the advance payment is set at between 5% and 30% of a sum equal to twelve times the initial amount of the contract inclusive of all taxes divided by its term expressed in months.
Where the contractor is a small or medium-sized enterprise or a craftsman within the meaning of article R. 2351-12, the minimum rate of the advance payment is increased to 30%.