The purpose of site scheduling, coordination and management is respectively to:
1° To analyse the basic tasks relating to design and works, to determine the sequence of these tasks and their critical path using graphic documents;
2° To harmonise in time and space the actions of the various parties involved at the works stage;
3° At the works stage, and until any reservations have been lifted within the time limits laid down in the public works contracts, to apply the various organisational measures adopted in the context of scheduling and coordination.