I. – When it has ruled on an application for authorisation of a group financial support agreement pursuant to I of Article L. 613-46-1, the supervisory board shall notify the parent undertaking of its reasoned decision within four months of receipt of the application. If the Supervisory Board remains silent at the end of this period, this shall constitute authorisation.
II. – When the supervisory board alone adopts a decision relating to a financial agreement pursuant to IV of Article L. 613-46-1, the parent undertaking and the competent authorities concerned are notified of the reasoned decision within four months of receipt of the request. If the Supervisory Board remains silent at the end of this period, the decision is deemed to have been authorised.
III. – Where the supervisory board adopts a decision that is consistent with that of the European Banking Authority pursuant to IV of Article L. 613-46-1, the parent undertaking is notified of the reasoned decision as soon as possible after the date of adoption of the decision of the European Banking Authority.