HOMOLOGATION REGISTER
The approval register, which is kept under the responsibility of the owner or the operator of the sports facility, contains the following information, which is essential for checks and updates:
– the dates and nature of the development and conversion work, in particular to the stands;
– the names of the contractor(s) and, if applicable, the project manager or technician responsible for supervising the work;
– the dates of the various checks and inspections and the observations to which these checks and inspections gave rise.
Copies of the following are attached:
– the documents making up the application;
– the latest approval order;
– the order to open the facility to the public referred to in article R. 143-39 of the French Construction and Housing Code.