The clauses of contracts concluded at provisional prices specify:
1° The conditions under which the definitive price will be determined, within the limit of a ceiling that may be revised;
2° The deadline by which the definitive price must be set;
3° The accounting rules with which the contractor must comply;
4° The documentary and on-site checks that the purchaser reserves the right to carry out on the technical and accounting elements of the cost price.