When the contract is concluded by a contracting authority, the amount of the amendment provided for in article R. 2194-2 may not exceed 50% of the amount of the initial contract.
Where several successive modifications are made, this limit applies to the amount of each modification.
The purpose of these successive modifications must not be to circumvent the advertising and competitive tendering obligations.