Article R4532-62 of the French Labour Code
From receipt of the contract signed by the contractor, the subcontractor has at least thirty days to draw up the specific safety plan. This period is reduced to eight days for finishing work in the case of a building operation or for ancillary work packages or work in the case of a civil engineering operation, provided that they are not on the list of work involving particular risks provided for…